Office Building Ravensburg

Construction Workspace in Ravensburg, Baden Württemberg, Germany

Office Building Ravensburg

The Ravensburg office building showcases the innovative synergy between the CREE System and the Office Zero wall system, combining prefabricated timber-concrete hybrid slabs with energy-efficient, low-emission wall elements. Beyond this technical integration, the project creates a healthy, high-quality working environment that reflects both sustainability and modern construction excellence.
Project Name
Office Building Ravensburg
Location
Wiesental 7, Ravensburg, Germany
GFA
4,760 m²
Start of construction
December 2024
CREE System assembly time
15 days
Completion
February 2026
Type of use
Commercial
Project stage
Construction
Height
20.5 m
Number of Floors above Ground
5
Number of buildings in total
1
CREE System Type
RSP Standard
Main CREE Project Partner
Matthäus Schmid
Main Client
MSB
Main Architect
Nething
Client
Voith
General Contractor
Rhomberg Bau
Structural Engineers
Statix
Subcontractors & Suppliers
Peikko
About

This office building in Ravensburg exemplifies a modern timber-concrete hybrid construction realized with the CREE System. By combining the natural warmth and ecological advantages of timber with the durability and fire protection of concrete, the project delivers a sustainable, future-oriented workplace.

Find the latest project learnings & details here

Prefabricated modular elements enabled a highly efficient and rapid construction process while maintaining flexibility for future adaptations. In fact, the five-story building, with a footprint of 915 m² per floor and a total gross floor area of 4,900 m², was fully assembled in just 15 days. Thanks to this speed, interior trades could already begin installations and drywall work on the ground floor while the upper floors were still being erected.

The project was delivered in partnership of Rhomberg Group with Matthäus Schmid Bauunternehmen. This Ravensburg project features an innovative synergy of two systems combined for the first time: the CREE System and the Office Zero wall system.

This combination of prefabricated timber-concrete hybrid slabs with energy-efficient, low-emission, easy-to-assemble Zero walls creates a forward-looking model for serial, high-performance timber construction. The hybrid construction achieves a Global Warming Potential (GWP) value more than 50% lower than conventional solid construction, while timber’s renewable nature and carbon storage capacity contribute to an excellent ecological footprint and a naturally comfortable indoor climate.

The building also adopts a future-oriented energy supply strategy through geothermal systems in combination with heat pumps, ensuring a nearly self-sufficient and resource-conserving solution. Achieving KfW-40 energy performance levels underscores the project’s commitment to sustainability. For its future occupants, this translates into a healthy, high-quality working environment with comfortable surfaces, excellent acoustics, and highly flexible office layouts that meet the needs of modern working models.

Highlights of the project include exceptional prefabrication levels that drastically reduce on-site workloads, ensuring speed, precision, and sustainability. Overall, this project stands as a pioneering reference for efficient, sustainable, and high-quality timber-hybrid office buildings, demonstrating how modern construction can meet the highest standards of speed, flexibility, and ecological responsibility.